Coastal GasLink stops work on section of pipeline route

Internal audit reveals clearing took place without valid archaeological impact assessments in place

Map of pipeline route showing location of Section 8 on which work has been stopped due to discrepancies with archaeological impact assessments. Coastal GasLink graphic.

Coastal GasLink (CGL) has stopped work on the last section of its pipeline project which runs from roughly south of Hazelton to Kitimat due to discrepencies with its archaelogical impact assessments.

In a statement on its website tonight, the company said it had discovered during an internal audit two areas where clearing has taken place in Section 8 contrary to its permits from the BC Oil and Gas Commission (OGC).

“At KP (kilometre post) 585, an area of approximately 600 metres long by 50 metres wide was cleared without an approved AIA in place,” the statement reads. “Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance. While clearing activities have taken place, minimal ground disturbance has occurred since the area has been used for transit and corduroy mats had been placed to limit disturbance.

READ MORE: NEB rejects federal review of Coastal GasLink pipeline

“At KP 631, due to a re-route, an area of approximately 240 metres by 10 metres was cleared without an AIA being completed. Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance”

CGL says it has voluntarily disclosed these incidents to (OGC), and the Environmental Assessment Office (EAO) and First Nations groups affected.

“Coastal GasLink is committed to protecting the environmental and cultural values of British Columbia during construction and operation of our natural gas pipeline,” said David Pfieffer, CGL president.

READ MORE: Gidimt’en launch civil lawsuit against Coastal GasLink

“Coastal GasLink regrets the errors that led to construction activities taking place without having approved archaeological impact assessments in place prior to start of construction.

“I have directed the team to complete a thorough investigation of these incidents and have halted clearing work in the area until the investigation is complete and recommendations are put into practice.

“I have also apologized to the impacted Indigenous communities and requested their participation in a proposed post-impact assessment.”



editor@interior-news.com

Like us on Facebook and follow us on Twitter

Just Posted

Bamfield Road safety concerns resurface after fatal bus crash

Huu-ay-aht First Nations wants a safe route between Bamfield and Port Alberni

2019 FEDERAL ELECTION: Meet the candidates for the Courtenay-Alberni riding

In an effort to inform the Courtenay-Alberni riding constituents, we have supplied… Continue reading

City of Port Alberni offers support after fatal bus crash

Two University of Victoria students killed after crash en route to Bamfield Marine Sciences Centre

Participants double at Parkinson’s Superwalk in Port Alberni

Second annual event also saw an increase in funds raised

Alberni School District considers three name changes

Neill Elementary, Ucluelet Secondary and school district identified for new names

Federal party leaders address gun violence after weekend shooting near Toronto

One teen was killed and five people injured in the shooting

Scheer makes quick campaign stop in Comox

Conservative leader highlights tax promises early in campaign

Conservatives promise tax cut that they say will address Liberal increases

Scheer says the cut would apply to the lowest income bracket

B.C. VIEWS: Cutting wood waste produces some bleeding

Value-added industry slowly grows as big sawmills close

Fewer trees, higher costs blamed for devastating downturn in B.C. forestry

Some say the high cost of logs is the major cause of the industry’s decline in B.C.

Federal food safety watchdog says batch of baby formula recalled

The agency says it’s conducting a food safety investigation

UVic president offers condolences after two students killed in bus crash

‘We also grieve with those closest to these members of our campus community,’ Cassels says

Coming Home: B.C. fire chief and disaster dog return from hurricane-ravaged Bahamas

The pair spent roughly one week on Great Abaco Island assisting in relief efforts

Most Read