Roller-compacted concrete at the stilling basin on the south bank of the Peace River for the Site C dam, September 2017. (B.C. Hydro)

B.C. VIEWS: Dam decision a big test for NDP

Alternatives to completing Site C not pleasant for John Horgan

It may seem far away to most readers, but the Site C dam decision facing the B.C. NDP government will affect you in more ways than just your electricity bill.

We’ve just had the latest round of overheated news coverage on the most expensive construction project ever undertaken in B.C., centred around the shocking revelation that the third dam on the Peace River is behind schedule and over budget. Of course those who were paying attention knew this weeks before, when B.C. Hydro CEO Chris O’Riley confirmed it in a letter to the B.C. Utilities Commission.

The cost estimate is approaching $10 billion, up from $8.3 billion when it began two years ago. And now with a one-year delay in diverting the river to perform the critical stage of construction, O’Riley says it can still be completed at the target year of 2024.

The commission’s review of the project was pushed through in a hurry at the direction of Premier John Horgan, who has committed to deciding whether to scrap the project or carry on with it by the end of 2017. This hasty report has resulted in a field day for the anti-dam industry that has sprung up around the project.

The short version of the commission’s report is that it would cost $10 billion to complete the most efficient hydro dam in North America, and $4 billion to stop it, wind up contracts that have been signed, and put the site back to the way it was.

The report discusses ways B.C. Hydro could provide additional power for a growing province without Site C. One way would be to use the smart grid that has been installed at great cost to implement “time-of-use” electricity pricing.

That means raising electricity rates at peak demand times, mainly early evenings, and lowering them at off-peak times. In political terms, Horgan would have to shut down the biggest construction project in the province, lay everyone off, and then tell people they should run their dishwashers and clothes dryers in the middle of the night.

Here’s a key quote from the review panel’s report:

“The panel believes increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers as the Site C project with an equal or lower unit energy cost.”

Note the word “could.” Geothermal energy is Green Party leader Andrew Weaver’s favourite topic these days, but nobody really knows how much that would cost to develop and connect to the B.C. Hydro grid.

As for “industrial curtailment,” that means shutting down mills and mines. The Horgan hardhat tour would likely be put on hold for a while.

Site C fake news has become a bit of an industry on its own, from fantastic claims about how many people could be fed by the strips of land that would be flooded, to a “tension crack” reported by one of the failed political candidates in the region that turned out to be an access road.

The two Indigenous chiefs who have had their anti-Site C cases tossed out of court across the country held one more media event at the legislature earlier this month. Meanwhile other Indigenous communities with project jobs and better territorial claims to the dam site await their fate once the political circus folds its tent.

Weaver has allowed that he won’t defeat the B.C. NDP government if it proceeds with Site C. But he continues to insist that thousands of new electric cars can be recharged with wind and solar power.

Tom Fletcher is B.C. legislature reporter and columnist for Black Press. Email: tfletcher@blackpress.ca


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

City of Port Alberni approves five-storey expansion at Tsawaayuus-Rainbow Gardens

Neighbours voice concern about traffic, loss of green space in wake of decision

Wounded Warriors runners arrive in Port Alberni

Fundraising dinner will take place at Royal Canadian Legion

Arrowvale Farm near Port Alberni hosts maple syrup fest

Taste west coast maple syrup on Leap Year Saturday and watch demonstrations too

ACRD urges B.C. gov’t to upgrade Bamfield Road in wake of winter storm

ACRD board to write letter to Premier John Horgan, expressing urgency

Toddler killed in Squamish grocery store parking lot

Child’s mother taken to hospital but her condition is not known

Two law enforcement trucks ‘deliberately’ set on fire in northern B.C., RCMP say

Police say they have video evidence of a person in the area of the truck fires

B.C. mother, daughter return home after coronavirus quarantine in Asia

Jensine Morabito and her daughter were on Holland America’s Westerdam but did not catch the virus

Leap Year means we get an extra day in February, so how are you spending it?

People online have a number of suggestions and plans on how they will be spending Saturday

Greta sticker that drew outrage in Alberta not child pornography: RCMP

X-Site Energy Services has denied having anything to do with the stickers

Bald eagle hit by train in northern B.C. has a chance of survival

The raptor has been taken to OWL in the Lower Mainland for recovery

Cheslatta Carrier Nation and Rio Tinto sign a historic agreement

Co-operation crucial to stem dropping Nechako Reservoir level

Hundreds of B.C. firefighters ‘climb the wall’ for BC Lung Association

The charity fundraiser saw participants climbing up 48 storeys

Most Read