Liberals’ 2-year infrastructure plan set to take 5: documents

Government says 793 projects totalling $1.8 billion in federal funds have been granted extensions

Late last year, officials warned that a federal spending spree to repair crumbling roads and water systems could take three years longer than expected to complete, based on internal documents outlining issues with the first tranche of cash in the federal government’s infrastructure program.

The federal government had originally hoped to have cities and provinces complete $5.4 billion in transit and water system work by this March, but quickly realized that more time was needed.

A “secret” fall briefing note to Infrastructure Minister Amarjeet Sohi, obtained by The Canadian Press through the Access to Information Act, says delays hampered a large number of construction projects, requiring that the deadline be extended as far as March 2021.

The heavily blacked-out document predicted the majority of water and transit projects “would require extensions not only for a third year, but beyond into a fourth year (i.e. 2019-20) and fifth year (i.e. 2020-21),” referencing the federal fiscal years in brackets.

Sohi agreed to a blanket deadline extension to March 2020, turning what was to be a two-year stimulus program into a four-year plan.

He said the decision to grant extra time to 2020, instead of 2021, was based on the expected cash flow for projects and the ability for construction companies to handle all the extra work.

“This is not about that projects are being delayed, it’s about taking a little longer to complete those projects or taking a little longer to have the buses manufactured because of construction and manufacturing capacity,” Sohi said in an interview from Edmonton.

“From our perspective, we made a commitment to build and rebuild infrastructure and focus on the repairs in phase 1 and … we are achieving the results we intended to achieve, but we also want to give flexibility.”

As of Friday, the federal government had approved more than 3,400 water and transit projects with a combined federal contribution valued at almost $4.2 billion. Of that money, federal coffers had only doled out about $175.6 million to date, based on figures available on the Infrastructure Canada website.

Federal dollars flow once cities and provinces submit receipts for reimbursement, often creating a lag between when work takes place and when the federal money is spent.

In some cases, the federal government won’t receive receipts until a project is completely done. In other cases, projects are delayed because of labour strife, bad weather or other factors beyond Ottawa’s control.

The government says 793 projects representing about $1.8 billion in federal contributions have been granted individual extensions from Sohi. Between those extensions, and delays in filing expense claims, federal officials last year decided to shift more than $2 billion in planned spending to future years.

Provincial and municipal officials say that the time needed to go through the funding approval process contributed to the delays.

Having officials vet the details of each proposal before getting federal approval for funding meant some cities put off breaking ground until they knew federal funding would come their way.

“We heard loud and clear from some municipalities that they were struggling to meet two pieces of criteria: timeline requirements and a provision that would require municipalities to incur 60 per cent of their costs by March 31st, 2018,” said Alex Benac, a spokesman for Ontario Infrastructure Minister Bob Chiarelli.

The extra time and removal of the local spending requirement, which Chiarelli asked for in September, has given cities “much-needed time to get shovels in the ground and keep their projects on track according to a more generous, achievable timeline,” Benac said.

Federal and provincial officials say the lessons learned from the first phase of the program will be used in designing the second phase.

Both sides want funding agreements for the second, longer and more lucrative phase of infrastructure spending signed by March.

Jordan Press, The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

Alberni hosts Island track and field championship

Secondary schools compete at Bob Dailey Stadium

Is Steve Nash Vancouver Island’s best athlete of all-time?

As Captain Canada gets ready to enter basketball’s Hall of Fame it’s time to debate his legacy

Who is Vancouver Island’s greatest athlete ever?

We want to know, you get to choose in a 64-athlete tournament bracket

200,000 salmon smolts released in netpens for Alberni salmon enhancement

West Coast Aquatic has released 205,000 chinook smolts into two net pens… Continue reading

Virtual simulation engages users in the event of a tsunami hitting Port Alberni

A team from the University of Victoria display a tsunami simulation at the 2018 #BCTECH Summit

VIDEO: Grand Forks shores up defences as floodwaters rise to peak levels

Canadian Forces, volunteers working to protect low-lying areas

B.C. Lions bring back 6-time all-star offensive lineman Jovan Olafioye

He was acquired by the Montreal Alouettes last year.

Whitecaps rally for 2-2 draw with FC Dallas

Vancouver climbed out of a two-nil hole to tie FC Dallas 2-2

B.C. VIEWS: Making sense of climate policy

Flood and fire predictions have poor track record so far

Chilliwack Chiefs moving on to RBC Cup final after thrilling win over Ottawa

Kaden Pickering scored the winning goal in the 3rd period as Chilliwack won their semi-final 3-2.

VIDEO: As floodwaters recede, crews assess the damage to Grand Forks’ downtown

More than four dozen firefighters and building inspectors came out to help

Wellington Dukes pull off epic upset of Wenatchee at RBC Cup

The Dukes are off to the championship game after downing the Wild 2-1 Saturday at Prospera Centre.

Canada to face U.S. for bronze at world hockey championship

Canada was looking to play in the gold medal game for a fourth straight year, but saw 3-2 loss

Searchers for Vancouver Island father turn focus to Cowichan River

Cowichan SAR joined by many other SAR groups, volunteers now determined to find missing man

Most Read